TO:  Shutdown Group, Facility Coordinators

FROM:  Service Response Center

DATE:  February 3, 2023
SUBJECT: Parking Garage Panel Foundation/Footer Installation Schedule


CDFD will be installing the foundations/footers for new parking garage pylons on the days listed below.  These new 13' tall pylons will distinctly establish the entrances to our campus parking garages.

February 6 – Monday – East Campus Garage – Dig (2) Footers, insert Sono tubes into hole to prevent collapse, cover holes with plywood sheeting and rope off with yellow caution tape.  The far exit lane from East Campus Garage to Forbes/Beeler will be closed temporarily.

February 7 – Tuesday – CIC Garage & Dithridge Garage – Dig (1) Footer each Garage, insert Sono tubes into hole to prevent collapse, cover hole with plywood sheeting and rope off with yellow caution tape.

February 8 – Wednesday – Set Steel Support Posts & Brace, Chris will request City Inspection, cover hole with plywood sheeting and rope off with yellow caution tape.

February 9 – Thursday – Inspection of Footers by City Inspector, Chris to meet City Inspector on site.

February 10 – Friday – Pour Concrete and Finish Concrete at (4) Locations.

For questions or concerns, please contact Kevin Ford, CDFD Project Manager, fordk@andrew.cmu.edu or 412-268-7853.