FMS- UPDATE-Wean Hall Power Shutdown 11/1 6AM – 7AM
UPDATE: The Wean Power Center 3 shutdown this morning is complete and everything is back to normal. Thank you for your cooperation during this period. On Tue, Oct 29, 2024…
UPDATE: The Wean Power Center 3 shutdown this morning is complete and everything is back to normal. Thank you for your cooperation during this period. On Tue, Oct 29, 2024…
Facilities, Infrastructure and Risk Management (FIRM) Facilities Management & Campus Services TO: Shutdown Group, CFA, Elevator Group FROM: Service Response Center SUBJECT: College of Fine Arts-South Elevator Outage, October…
Facilities, Infrastructure and Risk Management (FIRM) Facilities Management & Campus Services TO: Shutdown Group, SEI, 4721 Fifth Avenue FROM: Service Response Center SUBJECT: Reports of Power Outages, Tuesday, October…
UPDATE: The root cause of the recent power interruption has been identified as an issue at the Oakland substation. Duquesne Light Company (DLC) is actively working to restore the affected circuits…
Facilities, Infrastructure and Risk Management (FIRM) Facilities Management & Campus Services TO: Shutdown Group, SEI, 4721 Fifth, 4705 Fifth, 617 North Neville, Devonshire Road Residences, 618 Clyde (Highlands Apartments),…
UPDATED LISTING: The root cause of the recent power interruption has been identified as an issue at the Oakland substation. Duquesne Light Company (DLC) is actively working to restore the…
UPDATE: DLC is replacing a transformer and section of cable with an estimated restoration time of 6:00 PM. Some buildings may be earlier. 4705 Fifth and Neville Apartments restored. Thank…
RESTORATION UPDATE:The power has been restored and crews are checking all systems now. Thank you for your support and understanding, On Tue, Oct 15, 2024 at 3:20 PM FMS's shutdown notice…
TO: Shutdown Group, 300 SC, Facility Coordinators FROM: Service Response Center SUBJECT: Domestic Water Shutdown Notice for 300SC, October 19 There will be a domestic water shutdown Saturday, October…
Facilities, Infrastructure and Risk Management (FIRM) Facilities Management & Campus Services TO: Shutdown Group, Purnell Center, Facility Coordinators FROM: Service Response Center SUBJECT: Carpet installation in Purnell Center for…