TO:   Shutdown Group, CIC, Hamburg Hall

FROM:  Service Response Center

DATE:  September 25, 2015

SUBJECT:  CIC Exterior excavation at Drive Entrance 9/28 – 10/7

 

Exterior excavation work at the Northeast corner of the CIC building is scheduled between 9/28 thru 10/7.

 

This work includes removing the existing temporary small roof section at the curb level, excavation, waterproofing and pouring a new concrete sidewalk over the area.

 

The drive entrance between Hamburg Hall and CIC will remain open during this work, however there may be some short traffic stoppage during portions of the work.

 

Please use caution driving through this area and please pay attention to the closed areas of work.

 

If you have any questions, please call Service Response at 8-2910 or e-mail swetzel@andrew.cmu.edu.