FMS- Concrete Work – Morewood Drive at Cyert Center 4/28 – 4/30

Facilities, Infrastructure and Risk Management (FIRM)

Facilities Management & Campus Services

 

TO:  Shutdown Group, Housing, Morewood

FROM:  Service Response Center

DATE:  April 28, 2021

SUBJECT: Concrete Work – Morewood Drive at Cyert Center 4/28 – 4/30

 

Some minor concrete sidewalk and inlet work will occur in a portion of the drive behind Morewood Gardens between 4/28 until 4/30.

 

The area of repair is adjacent the Cyert Center for Early Education.

 

No noise will be created prior to 9:00AM and the contractor will limit work between the hours of 8:30AM – 9:45AM and 3PM – 4:30PM to accommodate the school’s drop off and pick up times.

 

There will be a partial restriction of the drive lane for these repairs, but this will not limit traffic in this one way section of the drive.

 

Please contact Ron Cunningham, FMS Principal Project Manager, at x8-1556 or rcunning@andrew.cmu.edu for any questions or concerns regarding this work. 

 

 