Facilities, Infrastructure and Risk Management (FIRM)
Facilities Management & Campus Services
TO: Shutdown Group, Facility Coordinator, CIC, Mellon Institute
FROM: Service Response Center
DATE: June 8, 2021
SUBJECT: Main Campus and CIC Electricity Transfer 6/9
Duquesne Light will need to remove a feeder from campus and the Robert Mehrabian Collaborative Innovation Center (CIC) Building starting tomorrow, 6/9, due to continued work on their substation.
Campus and Mellon Institute will be removed at 6AM tomorrow, 6/9, and will be restored at 6AM on 6/11. The campus and Mellon Institute will not experience any disruption to power during these times.
CIC will be removed at 7PM tomorrow evening, 6/9, and will be restored at 7PM on 6/10. The CIC Building will experience a short loss of power when the feeder is taken out of service and also when it is placed back in service.
Please contact Bob Penn, FMS Metering and Automation Systems Engineer, at 412-251-2658 or rpenn@andrew.cmu.edu for any questions or concerns regarding this shutdown.