Facilities, Infrastructure and Risk Management (FIRM)
Facilities Management & Campus Services
TO: Shutdown Group, Facility Coordinators, Housing
FROM: Service Response Center
SUBJECT: East West Walkway Replacement Project 6/15 – 8/8
Phase 4 of the East/West Walkway concrete replacement will begin today, 6/15, and is expected to be completed no later than 8/8.
The walkway will remain open to traffic until the temporary pedestrian walkway has been established to the entrance to Resnik from the Compass area. This will most likely occur at the end of this week 6/17/22.
Once the walkway has been closed for work all pedestrian traffic will be directed into the main hallway of Resnik for continuation on the previously completed areas of the walkway. The work area and temporary walkway are in the attached diagram.
Please contact Ron Cunningham, FMS Principal Project Manager, at rcunningham@andrew.cmu.edu for any questions or concerns regarding this work.