SUBJECT: Posner Hall Steam Line Replacement Work 6/22 – 8/1

 

Excavation and site work for the steam line replacement in front of Posner Hall will start on Wednesday, 6/22 and go until 8/1.  This work will take place Monday – Friday from 6AM – 3:30PM.

 

This work will be ongoing in the lawn area and the ramp leading up to the entrance of Posner Hall. Occupants are requested to utilize the entrance to Posner Hall from the sidewalk.  The accessible entry to Posner Hall will temporarily be via the Hall of Arts entrance.  Please see attached site plan with work area and fence layout.

 

Please contact Salonika Garapaty, CDFD Project Manager, at sgarapat@andrew.cmu.edu for any questions regarding this work.