TO:  Shutdown Group, Baker Hall

FROM:  Service Response Center

SUBJECT: Baker Hall Sprinkler Installation 5/18 – 6/22


As part of the Baker Hall 235/237 classroom renovation project, contractors will install a sprinkler system in the first and second floor hallways on the following days:

  • 2nd Floor Hallway: May 18th – May 29th

  • 1st Floor Hallway: June 1st – June 22nd

This work will take place between 6AM and 2PM each day.  There should be minimal noise and dust during this work. 

A portion of the hallway will be enclosed as a construction work area. A 5-foot corridor will remain open, and access to all offices will be maintained at all times.

Please reach out to Jan Held, CDFD Project Manager, at jheld@cmu.edu, if you have any questions or concerns.