SUBJECT: Mudge House Concrete Work: Morewood Ave Lane Restrictions 6/22-7/3
As part of ongoing summer improvements in the 5th & Morewood area, concrete work will begin at Mudge House during the week of June 22. This phase includes installation of a widened sidewalk and a reconfigured driveway.
During active concrete pours, Morewood Avenue will be reduced to one lane in each direction. Southbound traffic will be temporarily shifted into a northbound lane. Flaggers will be on site to safely direct vehicles through the work zone.
Work will take place on weekdays between 9AM and 3PM and is expected to be completed by Friday, July 3.